RR130-11 PEpC: A Breakthrough Project Delivery System That Improves Performance by Reforming Owner, Contractor, Supplier Relationships
Executive Summary:
This document reports on research, undertaken under the guidance of Construction Industry Institute Research Team 130, to develop a new and innovative project delivery system that reduces the time and cost of capital project execution without reducing quality and lifecycle performance. The motivation to undertake the work was based on the belief that the expertise embedded in the design of strategic procurement items and/or systems as well as the expertise needed for successful project integration is frequently lost or underutilized when suppliers are silent partners in the EPC process.
The three research objectives may be summarized as follows:
- To identify and recommend a step change in the EPC process so that the suppliers of strategic procurement items and/or systems may be brought into an expanded circle of cooperation between owner and contractor.
- To measure the impacts that this change will have on the EPC process.
- To provide a means to facilitate implementation.
The first objective was met by following a structured search for innovation, and defining PEpC (Procurement, Engineering, procurement and Construction) as
| an innovative project delivery system which makes it possible to utilize supplier expertise in all phases of the project life cycle by developing an advance procurement strategy and reaching agreement with suppliers on strategic procurement items and/or systems prior to the associated project engineering activities. |
The second objective was met by measuring the time and cost savings that could realistically be achieved when breakthrough changes brought about by PEpC were implemented. This analysis, based on ten theoretical implementation scenarios and four case studies, showed that savings in time between 10 and 15 percent and savings in total project labor cost between 4 and 8 percent were possible.
The third objective was met by developing a number of tools to assist in each step of a defined PEpC implementation process. Attainment of the objectives led to four principle conclusions. These were:
- There is a need to bring suppliers of strategic items and/or systems into the circle of cooperation between owner and contractor.
- A step change to the EPC process that achieves this result can be defined.
- Implementing PEpC will produce significant savings in the time and cost of the entire project delivery process.
- Implementing PEpC will require changing many existing procedures.
The research report concludes by recommending that PEpC be implemented on suitable projects, that CII expand and develop its current focus on supplier involvement in the capital project delivery process, and that additional research be carried out to resolve and confirm many issues which fall outside the scope and limitations of this report.
Table of Contents:
List of Tables
List of Figures
1. Introduction
1.1 Problem Statement
1.2 The Challenge
1.3 Outcome
1.4 Purpose of the Report
1.5 Research Objectives
1.6 Scope and Limitations
1.7 Research Methodology
1.8 Outline of the Report
1.9 Companion Documents
2. Literature Review
2.1 Introduction
2.2 Influence of TQM on Supplier Relationships
2.3 Procurement Management Literature
2.4 Construction
2.5 Conclusion
3. Analysis of Mail Questionnaire
3.1 Introduction
3.2 Questionnaire Design
3.3 Questionnaire Distribution and Return
3.4 Data Capture
3.5 Questionnaire Raw Data
3.6 Analysis of Part I Company Classification
3.7 Analysis of Part II
3.8 Analysis of Part III
3.9 Analysis of Part IV
3.10 Conclusions
4. Interviews by Research Team Members
4.1 Introduction
4.2 Methodology
4.3 Results of Key Issue Questions
4.4 Responses to Four Supplemental Questions
4.5 Conclusion
5. Survey of Associated Industries
5.1 Introduction
5.2 The Automotive Manufacturing Industry
5.3 The Micro-Electronics Construction Industry
5.4 Review
6. Defining PEpC
6.1 Defining PEpC
6.2 Key Concepts
6.3 Principle Tenets
6.4 A Developing Process
6.5 Review
7. Establishing a Baseline
7.1 Quantifying the Benefits of PEpC
7.2 The EPC Model Developed by RT 125
7.3 The Baseline Model
7.4 Comparison of Results
7.5 Scaling
7.6 Templates for Evaluating PEpC
7.7 Conclusion
8. Theoretical Scenarios
8.1 The Challenge
8.2 Scenarios
8.3 Theoretical Implementation Scenarios
8.4 DuPont Model
8.5 Summary of the Results
8.6 Conclusion
9. Field Implementations
8.1 Introduction
9.2 Case Study 1
9.3 Case Study 2
9.4 Case Study 3
9.5 Case Study 4
9.6 Emerson/Fischer-Rosemount Presentation
9.7 ABB Presentation
9.8 Comparison of Field Implementations
9.9 Comparison of Theoretical Scenarios and Field Implementations
9.10 Conclusion
10. PEpC Implementation
10.1 Overview
10.2 Project Delivery Systems
10.3 Technical Considerations
10.4 Organizational Considerations
10.5 Commercial Considerations
10.6 Change and Realignment of Core Competencies
10.7 Summary
11. Review of Core Competencies
11.1 Introduction
11.2 Competencies in the EPC and PEpC Process
11.3 Competencies Needed for PEpC
11.4 Alignment of Competencies for PEpC
11.5 Conclusions
12. Implementation Tools
12.1 Implementation
12.2 Implementation Steps
12.3 Implementation Tools
12.4 Achieving Results
12.5 Summary
13. Conclusions
13.1 A Challenge Met
13.2 Conclusions
13.3 Attainment of Objectives
14. Recommendations
14.1 Implementation
14.2 CII Focus
14.3 Future Research
Appendix A: Mail Questionnaire Sent to CII Member Companies
Appendix B: Example Database Format
Appendix C: Mail Questionnaire Results, All Records
Appendix D: Interview Document Used for Supplier Interviews
Appendix E: EPC Activity List Developed by RT 125
Appendix F: Survey Tool
Appendix G: Changes to the Baseline Model for the DuPont Flow Model
Appendix H: Case Study 1 Changes to the Baseline Model
Appendix I: Case Study 2 Changes to the Baseline Model
Appendix J: Case Study 3 Changes to the Baseline Model
Appendix K: Case Study 4 Changes to the Baseline Model
Appendix L: RT 111 Project Competencies and Definitions
References
|