The factor analysis and regression analysis performed in development of the ESP identified eleven factor groups with the most impact on estimate accuracy.
The figure below describes the eleven factors in order of significance. The most significant factor, basic process design, accounts for 25% of the estimate score therefore concludes that a comprehensive and definitive process design is critical to the accuracy of early estimates. Basic process design includes process flow sheets, heat and material balance, project schedule, capacities, equipment list, and P&IDs as the highest factors elements. (RS131-1, p. 9)