Schedule Reduction
Changes to the scope of a project beyond the final authorization inevitably result in longer duration and higher costs. Freezing of scope allows detailed design and material procurement to progress rapidly without rework and inefficiencies; and results in better budget accuracy with lower overall costs. Conceptual design and project definition should have progressed to the point that the authorization (definitive) cost estimate can be developed.
Evaluation of alternatives, value engineering, constructability input, and safety reviews should be completed before the scope is frozen. An effective change control process must also be in place. Team factors include a high level of trust among the owner, contractor, and other team personnel; inclusion of a user representative; and commitment to avoid scope growth, even if funds are available. Subdivision of the project into smaller components produces quicker and more concise definitions, resulting in shorter durations. Resistance to changes after a scope freeze must be driven by the owner Management. Costs for implementation of process changes that support early freeze should be weighed, but are usually relatively small. (RS41-1, p. 4)
Concurrent engineering changes the traditional engineering approach in two basic ways:
- End users and other project team members are actively involved in engineering activities as they are conducted, eliminating the need for formal end-of-activity reviews.
- Subsequent tasks are started earlier as bits of information become available, due to ongoing reviews and decision-making.
The following factors that can reduce project durations have been identified:
- Team members are responsible for the total project life cycle.
- Cross functional teams represent all major stakeholders.
- Early involvement of end-users in the design process.
- Aggressive schedules with monthly objectives and clear communication.
- Electronic software allows design groups to access common data.
Cycle time analysis is a formal review to ensure delivery of exactly what is needed, when it is needed, and the amount needed, while eliminating unnecessary activities from all functions of an organization. It can be used successfully in any phase of a project, and most effective when used with other schedule reduction techniques. The following practices are included:
- Form a cross-functional steering team of key stakeholders under the leadership of the project manager.
- Select a target process or focus area. Examples: inventory reduction, paperwork routing/approval, just-in-time manufacturing, or innovative construction sequences.
- Form teams for selected work areas and provide training in team dynamics and techniques.
- Map the overall work processes and identify problem areas (unnecessary steps, inconsistent handling, duplicated work, shared information, etc.).
- Select performance indicators, then measure, chart and post in each work area.
- Communicate the goals and progress of the analysis to employees involved with the process and provide them with necessary retraining.
- Use technology to provide common databases and automate information transfer and transactional type activity. (RS41-1, p. 18)
Use of more sophisticated EDM (electronic data management) technologies such as 3-D CADD and document imaging is likely to be commonplace in the near future. Maintaining a competitive edge, market expansion, increased productivity, and profit, will dictate that EDM tools become imperative. But they won’t produce successful projects unless good processes are in place for the project as a whole. EDM tools work well when used in conjunction with other SRTs (schedule reduction techniques): concurrent engineering, freeze of project scope, and cycle time analysis. Benefits include:
- Multi-locational access to process information
- Elimination of departmental ownership of information
- Improved process efficiency as demonstrated by reduced process cycle times
- Improved customer-supplier relations
- Access to real-time process information
RS41-1, Impact of Schedule Reduction Techniques over Project Life Cycle, (Appendix A)
- Based on the research team’s experience, a c)hart was developed showing the relative impact of a particular schedule reduction techniques (SRT during typical project life-cycle phases.
RS41-1, Deliverables Required Prior to Freezing Project Scope, (Appendix B)
- Early freezing of scope is valid for all projects, regardless of type or size.A structured process is needed for freezing of project scope to ensure all required deliverables are completed.