Achieving Zero Rework through Effective Supplier Quality Practices, Phase II

Publication No
RR308-12
Type
Academic Document
Publication Date
Aug 01, 2017
Pages
44
Research Team
RT-308
DOCUMENT DETAILS
Abstract
Key Findings
Filters & Tags
Abstract
The original question answered by RT 308 was “What are the most effective processes and practices for ensuring that project materials and equipment are produced, manufactured, or fabricated in strict accordance with all applicable specifications, and
Key Findings

During its Phase II research, RT-308 discovered the following impacts of supplier quality on product quality and inspection hours:

  • More NCs are found when the supplier’s facility is located in a developing country.
  • More inspection hours are budgeted and more NCs are found at the shop when supplier evaluation ratings are low. Additional money is spent to assure quality when these suppliers are selected.
  • Subcontracting, even for portions of a commodity like shop-fabricated piping, results in budgeted more hours of inspection.
  • More budgeted inspection hours are used when the supplier is NOT evaluated prior to award.
Filters & Tags
Project Phase
Research Topic
Achieving Zero Rework through Effective Supplier Quality Practices
Keywords
Cost of Non-quality, Total Landed Cost (TLC), Supplier Quality System, Number of Non-conformances, Quality Management, rt308