Model Planning and Controlling System for EPC of Industrial Projects

Publication No
RS6-3
Type
Research & Development Product
Publication Date
Apr 01, 1987
Pages
28
Research Team
RT-006g
DOCUMENT DETAILS
Abstract
Key Findings
Filters & Tags
Abstract
A typical industrial facility is an intricate arrangement of structures, vessels, machinery, piping, electrical systems, and instrumentation packed into a relatively small area. The engineering, procurement, construction, and start-up phases associate
Key Findings
It’s impossible to engineer and construct an industrial facility without some overlap of phases. Engineering often overlaps with procurement for vendor-engineered equipment, and with construction, for long time-phased projects. To the owner, life cycle costs are more important than design-construction costs, and these costs are balanced against potential revenues. The owner will directly overlap phases, to reduce overhead and time-value of investment costs, but such savings may be eroded by the costs of rework, idle crews, premium pay, team relations, morale, quality, and operational reliability. The approach described in this report is believed to be the one with the optimum overlap. No official claims are made, but users of the process feel comfortable with time savings in the order of 15% compared to the sequential approach, and construction labor savings as high as 30% compared to other fast-track options. Labor savings result from the detailed planning (plans & specs available at start of construction), materials availability when needed (procurement tracking and materials management), and productivity improvement. For the system to work, construction must defer to the needs of start-up, engineering must defer to the needs of procurement and construction, and procurement must defer to the needs of construction. There must be a continuous team approach to planning and execution that involves the owner, operator, engineer, procurement group, and constructor.
Filters & Tags
Research Topic
Cost/Schedule Controls
Keywords
Project controls, Planning and Scheduling, Change Management, Cost control, Scope and Execution Strategy, Work packaging, Estimating, Work Breakdown Structure, Schedule control, Code of Accounts, Schedule compression, Earned Value, rt6