Advanced Work Packaging: Design through Workface Execution, Version 2.1

Publication No
RS272-1
Type
Research & Development Product
Publication Date
Sep 01, 2013
Pages
28
Research Team
RT-272
DOCUMENT DETAILS
Abstract
Key Findings
Filters & Tags
Abstract
As projects have increased in complexity, their exposure to project failure in terms of budget and schedule has also increased. For sustained success, construction organizations that deliver complicated projects need practices that mitigate this expos
Key Findings

RT-272 created an execution model for AWP across the project life cycle over these three stages (RS272-1, p. 20).

  • Stage 1 – Preliminary Planning/Design
  • Stage 2 – Detailed Engineering
  • Stage 3 – Construction

Barriers to AWP implementation (RS272-1, p. 12) include the following:

  • Lack of clear implementation strategy
  • Lack of owner support for the process
  • Lack of clarity of contractual requirements for advanced work packaging
  • Lack of clear descriptions of role changes among personnel, including the new role of workface planner
  • Lack of champions and knowledgeable staff for organizations with limited AWP experience
  • Lack of support for increased resources and roles during planning
  • Lack of compatible information systems and handover requirements

A key contribution of RT-272 is the development of a consistent set of definitions for work packaging (RS272-1, p. 15). Definitions for the following terms are provided in the research:

  • Advanced Work Packaging
  • Workface Planning
  • Workface Planning Lead
  • Work Breakdown Structure
  • Engineering Work Package
  • Construction Work Package
  • Installation Work Package
Filters & Tags
Best Practice
Research Topic
Enhanced Work Packaging: Design through WorkFace Execution
Keywords
AWP, Scope Definition, Improved Labor Productivity, Reduced Schedule, Work Packaging, Constraint Management, rt272