Risk Assessment on International Projects: A Management Approach

Publication No
RS181-1
Type
Research & Development Product
Publication Date
Feb 01, 2004
Pages
38
Research Team
RT-181
DOCUMENT DETAILS
Abstract
Key Findings
Filters & Tags
Abstract
U.S. owners and contractors are aggressively pursuing international business opportunities and projects. While international projects may appear as attractive investments, such projects usually involve elevated levels of risk. The successful delivery
Key Findings

The IPRA can provide numerous benefits to the project team. These include uses as:

  • A checklist that a project team can use for determining potential project risks
  • Standardized risk terminology for international ventures
  • A process for identifying and assessing risk that will also facilitate prediction of disruptions, potential for disputes and other potential issues
  • A means to monitor progress in addressing risk control at various stages during the project’s life cycle
  • A tool that aids in communication and promotes alignment by highlighting poorly defined areas of risk for investors, owners, and design or construction contractor
 Refer to RS181-1 for a complete list of benefits. (RS181-1, p. 4)

A detailed list of the risk elements that impact the project’s life cycle (planning, design, construction, and operations) of international facilities was developed. The breakdown of the 82 risk elements grouped into 14 categories are not equal in impact to the threat/opportunity – as hypothesized by the team. Project characteristics affect the level of impact based on locale, project type, resource availability, government, and other specifics. Hence, the team created a standard guidance to assign the level of impact of a certain risk if no baseline previously existed based on a project’s characteristics. 

Refer to RS181-1 for a list of the categorized risk elements. (RS181-1, p. 5)

The likelihood of occurrence combined with the relative impact at the time of the assessment determines the relative importance of the risk (RS181-1, p. 23).

The top five critical go/no-go risk elements (RS181-1, p. 23):

  1. Sources and form of funding
  2. Business case
  3. Economic model/feasibility
  4. Political stability
  5. Contract type and procedures

For international construction projects, the following risk response is proposed as a critical phase of the overarching risk management process. These are suggested actions that can help the project team effectively implement the IPRA:

  1. Organize and formalize a risk management process and keep it as simple as possible.
  2. Begin early to be most effective.
  3. Keep a broad perspective to get the diversified input required.
  4. Undertake adequate pre-project planning, analysis, and engineering.
  5. Partner with owner and contractor management.
  6. Recognize that certain projects are more prone to risk and that experience in a jurisdiction is important.
  7. Risk documentation is critical.

(RS181-1 p. 27)

Filters & Tags
Best Practice
Research Topic
Risk Analysis for International Projects
Keywords
Risk Allocation, Risk Register, International Project(s), Risk Assessment, IPRA, Globalization, Risk Elements, Risk Matrix/Matrices, Likelihood of Occurrence, rt181