Making the Case for Advanced Work Packaging as a Standard (Best) Practice
Publication No
RS319-1
Type
Research & Development Product
Publication Date
Nov 01, 2015
Pages
34
Research Team
RT-319
DOCUMENT DETAILS
Abstract
Key Findings
Filters & Tags
Abstract
Key Findings
When properly implemented, AWP supports substantial project performance improvement. AWP implementation depends on the accomplishments of three prerequisites during the implementation process: (RS319-1, p. 7)
- Process adherence to prescribed AWP guidelines
- Organizational alignment within the project management team on AWP deliverables
- Contract integration of AWP procedures among key project participants
Prior research by RT-272 conceptualized three incremental levels of AWP implementation maturity, and the Maturity Model characterizes these stages in terms of work processes and required capabilities, recommending a stepwise progression through the levels to achieve full AWP benefits. (RS319-1, p. 21)
- AWP Early Stages
- AWP Effectiveness
- AWP Business Transformation
Companies have introduced AWP for the first time, possibly on a pilot project. Companies have adopted prescribed guidelines and procedures, either to test their effectiveness for limited portions of the project or to fulfill a stakeholder requirement to adopt AWP. A potential barrier at this stage is top management commitment, so a key point is that AWP adoption is initially a top-down process that is expected to generate aversion to change. (RS319-1, p. 28)
AWP becomes part of the project strategy at this stage of maturity, including part of major stakeholder’s contracts, aligning payment and control activities with the various engineering and construction deliverables. Companies achieve major performance improvements, consistently bringing down budget and schedule estimates.
(RS3109-1, p. 29)
(RS3109-1, p. 29)
Organizations within this group have acquired substantial AWP maturity and have mastered and implemented AWP procedures across multiple projects at once. For example, organizations as this level of maturity have: (RS319-1, p. 30)
- Project Setup and Execution – Written practices and procedures, change management systems, engineering and construction work packages, scheduling, and progress measurement are all in-place.
- Construction Focused – Well thought out CWP (construction work plan), materials delivery dates integrated into schedule, and effective construction input during FEP are all in-place.
- Integrated Date Systems – Statusing systems, constraint analysis, checkout and startup practices, and IWP (installation work packages) are all in-place.
Filters & Tags
Knowledge Area
Best Practice
Project Phase
Project Function
Industry Group
Research Topic
Transforming the Industry: Making the Case for AWP as a Standard (Best) Practice
Keywords
AWP,
advanced work packaging,
maturity model,
business transformation,
AWP maturity,
implementation maturity,
rt319