Pre-Project Planning Tool: PDRI for Buildings

Publication No
RS155-1
Type
Research & Development Product
Publication Date
Oct 01, 1999
Pages
25
Research Team
RT-155
DOCUMENT DETAILS
Abstract
Key Findings
Filters & Tags
Abstract
Previous CII research found that tools for measuring project scope definition and assisting alignment between project participants needed to be developed. CII formed the Project Definition Rating Index for Building Projects Research Team (RT 155) to p
Key Findings
PDRI–Buildings is limited to developing scope for building projects, excluding residential houses, performed in both the private and the public sector and has limited applicability to the infrastructure sector. Therefore, the findings from this research are most applicable to the multi-story or single-story commercial, institutional, or light industrial facilities. (RS155-1, p. 1)

This research identified 64 critical elements for the building projects scope definition package and grouped them into the following 11 categories: (RS155-1, p. 3) 

  • Business Strategy – 8 elements
  • Owner Philosophies – 4 elements
  • Project Requirements – 6 elements
  • Site Information – 8 elements
  • Building Programming – 13 elements
  • Building/Project Design Parameters – 8 elements
  • Equipment – 3 elements
  • Procurement Strategy – 2 elements
  • Deliverables – 2 elements
  • Project Control – 5 elements
  • Project Execution Plan – 5 elements
Proper scope definition during pre-project planning will improve both the cost and cycle time needed to design and construct capital facilities. (RS155-1, p. 19)

PDRI is best used as a tool to help project managers, project coordinators, and project planners organize and monitor progress of the pre-project planning effort (RS155-1, p. 9). Lessons learned include:

  • Scoring should ideally be done several times during pre-project planning. A minimum of two times is recommended.
  • Using the tool is an excellent way to align a project team
  • PDRI–Buildings is effective even when used very early in the planning process. Individual planners can use the tool at this point to identify potential problems and to organize their work effort.
  • The PDRI is of little value unless the user takes action based on the analysis and uses the score in managing their projects.
This PDRI tool can be customized to fit the needs of almost any organization. Elements that are not applicable can be zeroed out, thus eliminating them from the final scoring evaluation. (RS155-1, p. 17)
Filters & Tags
Best Practice
Industry Group
Research Topic
PDRI for General Building Projects
Keywords
Project Definition Rating Index, Front End Planning, Pre-Project Planning, Scope Definition, Risk Management, PDRI Buildings, Commercial, Institutional, rt155